We have established a project schedule for Phase 1 of the new Holy Family School. This is a target timeline, and it can be affected by things like weather or supply chain issues.
4/21/2023 - Ceremonial Groundbreaking - COMPLETED
5/05/2023 - 98% design drawing completion - COMPLETED
5/31/2023 - Final Design Development from Chapman Sisson Architects - COMPLETED
6/15/2023 - Final pricing from General Contractor Fite Building Company- COMPLETED
6/15/2023 - Variances granted by Huntsville Planning Commission- COMPLETED
6/20/2023 - Final City and State Approvals- COMPLETED
7/15/2023 - Final Approval and Contract signing by Bishop Raica- COMPLETED
8/15/2023 - Begin Construction - SCHEDULED TO BEGIN FIRST WEEK IN AUGUST 2023
Dec 2024 - Construction completion and occupancy