Holy Family School Phase 1 Construction Project Schedule
Now that the Ceremonial Groundbreaking has been held for the new Holy Family School Phase 1 Project, the schedule for the project is a point of curiosity. A tentative project schedule follows. This schedule can be positively or negatively affected by things like weather, supply chain issues, etc. but this is the target schedule
4/21/2023 - Ceremonial Groundbreaking - COMPLETED
5/05/2023 - 98% design drawing completion - COMPLETED
5/31/2023 - Final Design Development from Chapman Sisson Architects - COMPLETED
6/15/2023 - Final pricing from General Contractor Fite Building Company
6/15/2023 - Variances granted by Huntsville Planning Commission
6/20/2023 - Final City and State Approvals
7/15/2023 - Final Approval and Contract signing by Bishop Raica
8/15/2023 - Begin Construction
Dec 2024 - Construction completion and occupancy